The Construction Project Went Over Budget: Measuring the Financial Impact (Part II of II)

Construction projects do not usually go as planned and sometimes, when delays and overruns occur, questions arise regarding fault and damages. A project can leave an unmistakable financial trail and still present a difficult causation question. This is a two-part series article, read Part I here. This article is the second article of this two-part series, The author in this part focuses on what is the measure of economic damages and what is excluded in the analysis.


Once the construction findings define the financial scope, the analyst turns to the resulting economic consequences. Consider a project budgeted at $10 million that finished at $13 million. Subtracting one figure from the other takes seconds and settles almost nothing. The $3 million gap provides the starting variance for the damages analysis.

That gap can hold changed work, delay and disruption cost, estimating deficiencies, contractor-caused inefficiency, unrelated escalation, and costs that would have been incurred no matter what. Some of it may already have been paid through change orders, and elsewhere the project may have produced savings or avoided costs.

Defining the Damages Analysis

The phrase “Who pays?” frames the dispute, but it is not a question the financial analyst decides. Counsel evaluates the contract, entitlement, and the governing legal standards. The trier of fact or other decisionmaker resolves liability and responsibility. The analyst quantifies the economic effect under the accepted legal and technical assumptions. Where those assumptions remain disputed, the analyst measures the financial result under alternative scenarios.

A common analytical error is treating the $3 million variance as the damages conclusion. The analysis instead determines what portion of the variance the events at issue explain. The resulting damages may be lower than the gross overrun after unrelated costs, prior payments, savings, and offsets are considered. In some matters, separate economic effects, such as lost profits, may also fall outside the project-cost variance.

What replaces that number is a sequence, and the rest of this article follows it: start with the event and its scope, identify the but-for condition, select a method the records support, test whether each claimed cost is incremental by category, and reconcile the result to net damages.

To see the sequence at work, follow a single claim through it: the contractor attributes a 90-day extension to a delayed approval and claims $750,000.

The Event, Scope, and Affected Period

The financial assignment begins with the technical findings: the event under review, the affected activities or trades, the period of impact, and whether the project experienced delay, disruption, acceleration, resequencing, added work, or another condition. Those findings define which records to open and which questions to ask. In this claim, the technical findings support 60 of the 90 days the contractor assumes, so part of the claimed period drops out before a single cost is tested.

A supported extension may direct attention to supervision, field office, equipment, insurance, temporary facilities, financing, and other costs that vary with duration. A disruption finding on a specific trade may direct attention to labor hours, installed quantities, equipment use, and the costs of the affected work. An acceleration finding may call for review of overtime premiums, added shifts, staffing changes, supervision, and expediting.

The connection should be evaluated by cost category. A 90-day extension does not turn every cost recorded in those 90 days into an incremental one. Some would have been incurred regardless. Others belong to work outside the affected activities, or to a separate event. The analyst should establish a supported period and causal assumption for each category. Applying one global delay period across the entire claim can sweep in unrelated costs. Financing, interest, and carrying costs deserve particular care, because whether and how they are recoverable depends on the contract, the governing law, and the assumptions the analyst is instructed to apply.

Disruption requires evidence supporting a reasonable measure of the added cost caused by reduced productivity, after accounting for other factors affecting the trade’s total cost.

Where a project event also affects business income, the same discipline applies: the lost profit must be tied to the event, built on a supported but-for condition, and reduced by the costs avoided when the revenue was not earned.

When the technical assumptions remain disputed, the model should be able to show the financial result under alternatives. For example, the 60-day period supported by the technical findings can be compared with the contractor’s 90-day assumption. Costs tied to one affected trade can likewise be separated from costs tied to another. The analyst can quantify those alternatives without endorsing an alternative technical conclusion.

Developing the But-For Condition

The analyst compares the actual result with the result that likely would have occurred without the events treated as compensable under the accepted legal and technical assumptions. In construction matters this is often put in practical terms: what the project should have cost, or how the business should have performed, under the accepted assumptions.

The estimate and actual cost are both relevant inputs, but each requires testing. The estimate may contain quantity errors, omitted scope, aggressive productivity assumptions, insufficient escalation or contingency, or a plan that changed for reasons unrelated to the dispute. Actual cost may include rework, inefficiency, unrelated escalation, scope growth, costs outside the relevant period, or amounts that would have been incurred regardless.

So, the but-for analysis needs a bridge. The analyst starts from the estimate, budget, or other benchmark, tests whether it reasonably represents the expected condition, and adjusts it where the record supports an adjustment. The actual results are then measured against that supported benchmark; within the activities and periods the construction findings define. For the claim, that means setting a but-for baseline, namely what the project would have cost without the delayed approval, tested rather than assumed.

Choosing a Damages Method

Where the records isolate specific incremental costs tied to the established events, an actual cost approach is usually the most direct. The analyst traces the amount to source records, confirms the period, and asks whether the cost would have been incurred absent the event.

Where specific isolation is not practical, a modified total cost approach may come into play. It starts with a broader variance but adjusts, with evidence, for estimating deficiencies, unreasonable costs, claimant-caused conditions, and unrelated overruns.

A total cost presentation assigns the entire difference between actual cost and the original bid or budget to the event under review. It assumes, among other things, that the estimate was reasonable, that actual costs were reasonable, and that the claimant did not cause the overrun. Because the method depends on those assumptions and provides less event-specific isolation, it is particularly sensitive to weaknesses in the estimate, actual costs, and allocation of responsibility.

Disruption and lost productivity call for a different type of measurement. They are often evaluated through comparison-based approaches, including a measured-mile analysis when reliable comparable periods exist. The construction or productivity expert ordinarily develops the technical analysis, while the financial analyst evaluates and quantifies the resulting financial consequences under the accepted findings. Where no reliable comparison period exists, the limitation should be identified and reflected in the analysis.

The quality of the records shapes the available method. Detailed cost codes, labor distributions, invoices, equipment logs, and maintained project records may allow a direct analysis. Aggregated or incomplete records may force allocation or approximation, and the limitation should be disclosed plainly. Whether an actual cost approach fits the claim depends on whether the supervision, field office, and equipment tied to those 60 days can be isolated in the records. If not, a modified total cost approach may be considered, but its assumptions, allocations, and adjustments still require support.

Incremental Cost Analysis

Testing whether a cost is incremental means reading two record sets against each other. Project records and financial records answer different questions. Project records help establish what happened, when, which work was affected, and how performance changed. Financial records establish what was incurred, when it was booked, who incurred it, whether it was paid or reimbursed, and whether it shows up elsewhere in the claim.

A daily report may record that a crew lost access to an area, but it puts no dollar figure on the idle time. An equipment invoice fixes a monthly rental charge without explaining why the machine stayed on site, or whether the whole rental period ties to the disputed event.

The analyst should reconcile the two record sets where possible and explain unresolved differences. If the chronology puts the impact in June but the claim reaches back to March, the discrepancy should be investigated. If a change order already paid for added labor and that same labor still sits in the damages model, the analysis may be carrying a prior payment. If the finding affects one trade but the job-cost report buries several trades in one cost code, the allocation should be supported or the limitation disclosed.

An inconsistency is not resolved by picking the record that yields the preferred number. It should be investigated, explained, and reflected in the calculation. Sometimes the records support a range of outcomes rather than a single forced reconciliation. Tested by category, the claim sheds more: some supervision would have remained on site regardless, and one equipment rental continued for a reason unrelated to the approval, so neither is incremental to the delayed approval, regardless of when the cost was recorded.

Reconciling Net Damages

Economic damages should reflect the net incremental harm attributable to the compensable events under the accepted assumptions. That means attending to the amounts that reduce, replace, or duplicate the claimed loss.

Change-order payments and prior reimbursements may already cover part of the claimed cost. Scope reductions and project savings may offset added spending. Mitigation may shrink the duration or amount of the loss, even where the mitigation itself carries a cost. The treatment of these offsets, including insurance and third-party recoveries, may vary with the contract, jurisdiction, and remedy. The analyst should therefore identify the treatment assumed in the calculation. Avoided costs should be addressed when the event prevented an expenditure, or when a revenue-based claim includes costs that would have been spent to earn the revenue.

Double counting is a standing risk because construction claims so often carry overlapping categories. A generator can show up as temporary power and again as equipment rental. A sales concession can be counted separately while the same revenue effect is also included in the lost profits calculation. Reconciling to the general ledger and cross-checking among categories are the basic controls against these overlaps.

Reconciliation brings the calculation to a net amount under the accepted assumptions. A $125,000 change order has already paid for part of the claimed labor, and the same superintendent appears in two claim categories. With the period cut to 60 days and the non-incremental supervision and unrelated equipment already removed, the $750,000 figure resolves to a supported net well below its face amount.

A construction overrun tells you the size of the variance. An economic damage opinion should explain the portion tied to the established events, the method used to measure it, and the adjustments needed to reach a net result. The final number stays conditional on the legal and technical assumptions, but the financial reasoning behind it should remain traceable even as those assumptions change.


Daniel Basch, CPA, ABV, CFF, CVA, is Vice President, Economic Consulting, at Aperture. He advises attorneys, insurers, businesses, owners, and contractors on economic damages, forensic accounting, business valuation, and related financial issues in disputes and transactions. His work includes lost profits, business interruption, claimed damages, expert rebuttal, and construction-related financial analysis. Mr. Basch serves as an expert witness and prepares expert reports and financial analyses for use in disputes. He also serves in professional leadership roles with the AICPA and FICPA focused on credentialing, examination development, and professional education.

Mr. Basch may be contacted at (941) 773-7806 or by e-mail to dan.basch@aperturellc.com.

The National Association of Certified Valuators and Analysts (NACVA) supports the users of business and intangible asset valuation services and financial forensic services, including damages determinations of all kinds and fraud detection and prevention, by training and certifying financial professionals in these disciplines.